8/24/2015 Update

Crews from Q3, an authorized CenterPoint Energy contractor, completed restoration within the scope of the Reservoir Boulevard construction project.

We understand that the Reservoir Boulevard construction project was an inconvenience to people living and commuting in and around the area, so we greatly appreciate your patience and understanding as we worked to complete restoration as safely and quickly as possible.

If you have questions regarding CenterPoint Energy's 
restoration, please call 612-321-5042. Thank you. 


8/3/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished replacing service lines within the scope of the Reservoir Boulevard NE construction project.

Crews from Q3, an autho​​rized CenterPoint Energy contractor, will begin restoration shortly.

Please continue to visit CenterPoint Energy's website for the final Reservoir Boulevard NE restoration update. Thank you. ​

7/21/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished replacing service lines along both the east and west side of Reservoir Boulevard.

Crews are currently replacing service lines along Arthur Street NE and will continue working towards 45th Avenue NE.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Crews anticipate completing construction next Friday, July 31.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you. ​​​


7/10/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution within the scope of this project last Tuesday, July 7.

Service line replacements along 42nd Avenue NE and along the west side of Reservoir Boulevard are now complete.

Crews continue replacing scattered service lines along of Reservoir Boulevard, working south to north.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you. ​​


7/1/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, continue installing natural gas distribution along the west side of Arthur Street and along the north side of 42nd Avenue NE.

Crews anticipate completing the installation of natural gas distribution pipe in the above areas by Monday, July 6th.  

Crews will finished replacing service lines along 42nd Avenue NE today, Wednesday, July 1st.

Crews will then begin replacing service lines along the east side of Reservoir Boulevard, working south to north. Crews anticipate replacing service lines along Reservoir Boulevard for the next week, weather permitting.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​

6/22/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution along the east side of Reservoir Boulevard NE, from Gould Avenue NE to 44th Avenue NE.

Crews are now installing natural gas distribution pipe eastwards along 44th Avenue NE toward Stinson Boulevard. Crews anticipate working along this street for the remainder of the week.

Crews finished replacing service lines along Gould Avenue NE. Crews are currently replacing service lines along 42nd Avenue NE.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please anticipate intermittent parking lane closures as construction continues.
Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.

6/10/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution along the west side of Reservoir Boulevard NE, from Gould Avenue NE to 44th Avenue NE.

Crews are now installing natural gas distribution pipe along the east side of Reservoir Boulevard NE, from Gould Avenue NE to 44th Avenue NE. Crews anticipate reaching 44th Avenue N. by the end of next week.

Crews are currently replacing service lines at Gould Avenue NE. After Gould Avenue NE. is complete, crews will begin replacing service lines along 42nd Avenue NE.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property.

Please anticipate intermittent parking lane closures as crews advance northwards.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.

6/1/2015 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, started installing natural gas distribution pipe near the intersection of Gould Avenue NE and Reservoir Boulevard NE this past Friday, May 29th.

Crews will continue to install natural gas distribution pipe northwards along both the east and west side of Reservoir Boulevard NE. Please anticipate intermittent parking lane closures as crews advance northwards.

Crews will be working from 7:00 a.m. to 7:00 p.m. Traffic control will be removed at the end of each workday.

By Friday, June 5th, crews anticipate reaching 44th Avenue N. and Reservoir Boulevard NE.

Please visit our website often to receive project updates, traffic alerts and any anticipated road or lane closures. Thank you.​