​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Columbia Heights/Fridley ​​- 2nd Street NE​​​

​​​Scheduled Start Date: March 29, 2016​​​​

​​​​Project Description ​​​

In preparation for a City of Fridley 2016 paving project, Michels Corporation, an authorized CenterPoint Energy contractor, will upgrade approximately 9,000 feet of natural gas pipeline ​along 2nd Street NE, 2 1/2 Street NE and 3rd Street NE, from 49th Avenue NE to 44th Avenue NE (see map below for detail).

The work will also include the replacement of 140 natural gas service lines. ​Construction is expected to start on March 29, 2016 and will require approximately three months to complete the work.​