Project Status - Brooklyn Center - 72nd Avenue N.

5/16/2017

Crews from Michels Corporation, an authorized contractor for CenterPoint Energy, will finish Phase 2 of 3 on the 72nd Avenue N. project in Brooklyn Center by this Friday, May 19, or early within the week of May 22.

Crews from Q3, an authorized contractor for CenterPoint Energy, will be restoring the areas affected by construction.

CenterPoint Energy wants to thank the residents and customers for their patience.​


5/4/2017

Crews from Michels Corporation, an authorized contractor for CenterPoint Energy, have finished Phase 2 of 3 on Emerson Avenue N. from 73rd to 70th Avenues N. They are currently working on Fremont Avenue N. between 73rd and 70th Avenues N. They anticipate finishing Fremont Avenue N. within the week of May 8 or 15.

The remaining streets after Fremont Avenue N. are Girard Avenue N. and 72nd Avenue N. (Please see the map below.) ​


4/27/2017

Crews from Michels Corporation, an authorized contractor for CenterPoint Energy, have finished installing all the new natural gas mains on the 72nd Avenue N. project from Humboldt to Camden Avenues N. and from 73rd to 70th Avenues N. (Phase 1). Phase 1 is complete on the 72nd Avenue N. project.

The crews also connected the natural gas service lines to the new mains on all the streets east of Dupont Avenue N. in the construction area (Phase 2). The finished streets are the following: Woodbine Lane, Bryant Avenue N., Aldrich Court N., Camden Avenue N. and 72nd Avenue N. east of Dupont Avenue N.

The crews are continuing Phase 2 on the streets west of Dupont Avenue N. where the new mains were installed. The estimated end date for Phase 2 is May 12. After Phase 2 is done, crews from Q3, an authorized contractor for CenterPoint Energy, will restore the areas affected by construction. ​



4/13/2017

Crews from Michels Corporation, an authorized contractor for CenterPoint Energy, have started Phase 2 (connecting the natural gas service lines to the new main) today on April 13. They are working on Phase 2 concurrently while they’re working on Phase 1 (installing natural gas mains). (Please see our update from April 12 to know where the Phase 1 crews are going and what they’ve finished so far.)

The Phase 2 crews are working on Woodbine Lane, Camden Avenue N., Bryant Avenue N. and Aldrich Court N. They will be working there until the end of the week of April 17. ​


4/12/2017

Crews from Michels Corporation, an authorized contractor for CenterPoint Energy, have been working on Phases 1 and 2 on the 72nd Avenue N. project in Brooklyn Center.

As of April 12, crews have installed new natural gas mains (Phase 1) on all the streets east of Dupont Avenue N., highlighted in yellow on the map. Wherever the crews have installed new gas mains, the crews are going back along the same construction route to connect natural gas service lines to the newly-installed mains (Phase 2).

Currently during this week, the crews have been installing new mains (Phase 1) on Emerson, Fremont and Girard Avenues N. They are moving west on this project.​


4/6/2017

Crews from Michels Corporation, an authorized contractor for CenterPoint Energy, have started Phase 1 of the 72nd Avenue N. project on Wednesday, April 5. The crews are working on Camden Avenue N., Woodbine Avenue N. and 72nd Avenue N. near Camden Avenue N., working their way west.


By the end of the week of April 3, the crews expect to be done with Phase 1 on the streets east of Dupont Avenue N.


Next week during the week of April 10, the crews will begin Phase 2 of the project, which is connecting the natural gas service lines to the new main along the same construction route. The crews will start on Camden Avenue N. and work west on the streets where work was previously done for Phase 1.​



3/16/2017

What is CenterPoint Energy doing for construction?

Crews from CenterPoint Energy will begin replacing an existing natural gas pipeline in Brooklyn Center the week of April 3, 2017. Project construction is expected to last until July 2017. (Any changes in project dates will be noted on CenterPoint Energy’s website.) Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas mains between the streets of 73rd Avenue N., 69th Avenue N., Humboldt Avenue N. and Camden Avenue N.​

Lane restrictions are anticipated in areas where active construction is occurring. The lane restrictions are necessary to keep both the public and construction personnel safe.

Construction typically happens in three phases:

  • Phase 1 is installing the natural gas distribution main.
  • Phase 2 is connecting the natural gas service lines to the new main along the same construction route. (A gas service line is a small-diameter pipe connecting the customer's gas service to the main line in the street.)
  • Phase 3 is restoring the areas affected by construction--typically the utility easement, the street, and the customer's yard.

How may construction affect customers?

As part of this main project, the crews will also be replacing several natural gas service lines that connect from the main to the customer's property. Customers will experience a short disruption of gas service as the crews are installing the gas service line. 

Crews may have to dig in the ground on your property in the utility easement to complete the task of service and main distribution line replacement. If a customer’s property is disturbed, CenterPoint Energy will restore the hard and soft surfaces affected by construction at no cost to you.

How can I contact CenterPoint Energy?

CenterPoint Energy wants to thank you for your patience. For questions about the project, please call our Information Hotline at 612-321-5369 or our Communication Specialist at 612-321-5546. For questions about restoration (hard or soft surfaces) please call our Restoration Department at 612-321-5042.