​​​​​Project Status - Bloomington - Drew Avenue S. 

​5/4/2016 Update

All service line replacements within the scope of this project are now complete!

Crews from Q3, an authorized CenterPoint Energy contractor, will restore all soft surface areas shortly. The City of Bloomington will repave the roads in this area. Thank you.

​4/21/2016 Update

Beginning Monday, April 25, the right northbound France Avenue N. lane will be closed near Canterbury Drive for approximately two to three days.

By the end of next week, all remaining scattered service line replacements will be complete. Crews from Q3, an authorized CenterPoint Energy contractor, will restore all soft surface areas.

Please note the City of Bloomington will be repaving the roads in this area. Thank you.

​4/13/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, finished installing natural gas distribution pipe within the scope of the Drew Avenue S. project last week.

Representatives from CenterPoint Energy will continue to contact residents whose gas service may be affected to schedule the necessary construction work on their property. If the gas meter is located inside your home or building, we will move it to an outside location.

The crew onsite is replacing approximately four to five service lines per day at scattered locations throughout the project and anticipates continuing through the end of April.​ Thank you. 


​4/1/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, are currently installing the final stretch of pipeline along the north side of Canterbury Road.

On Monday, April 4, crews will begin replacing service lines, working the project north to south.

Representatives from CenterPoint Energy will contact residents whose gas service may be affected to schedule the necessary construction work on their property. If the gas meter is located inside your home or building, we will move it to an outside location. 

Crews replace approximately five service lines per day and anticipate working for the next one and a half weeks, weather permitting.

For more information, please visit our website. Thank you.​

​3/24/2016 Update

Crews from Michels Corporation, an authorized CenterPoint Energy contractor, will begin installing natural gas distribution pipe near the intersection of 102nd Street W. and Drew Avenue S. on Monday, March 28.

Crews will be installing pipe southwards along the east side of Drew Avenue S. and moving to the west side of Drew Avenue S. after reaching 103rd Street W.

Crews will also install pipe along the north side of 103rd Street W., moving towards 104th Street W.  

Crews anticipate working the above streets through the remainder of next week.

For more information, please visit our website. Thank you.
​​